Accepting a Sandvik Crusher On Site: An 8-Step Checklist I Actually Use

2026-11-20 · Bogdan Ionescu · Field Engineering

Scope: Who This Checklist Is For

If you're the person standing on a quarry pad in steel-toe boots, walkie-talkie in hand, watching a lowboy roll in with a piece of rock processing equipment on it—this is for you. I've been that person. Quality and brand compliance manager at a mid-size aggregates operation, reviewing everything from 60,000-lb jaw crushers to pallets of spare liners before it goes into service. In our Q1 2024 audit alone, I rejected roughly 30% of first-delivery items over specification gaps that could've been caught before the truck left the dealer's yard.

Quick scope note before we start: this is for industrial rock processing equipment. Sandvik QJ341 jaw crushers, 800i series cone crushers, those kinds of machines. If you're here looking for a "can crusher yeti" setup or a "bucket golf" arrangement, that's a different blog and a completely different price point. The rules below are meant for six-figure capital equipment, not for tailgating gear.

Here's what I've learned the hard way: most acceptance inspections fail not because the machine is bad, but because the inspector checked the wrong things. I've been that inspector. So here are the eight steps I actually run now, in order, every time.

Step 1: Pull the Serial Plate Before You Touch Anything

Before you climb on the machine, photograph the serial plate. Then photograph it again from an angle. Compare it against the bill of lading, the purchase order, and—this is the part people skip—the dealer's configuration sheet.

I said "spec sheet." The dealer heard "model brochure." Those aren't the same document, and I only discovered that when our delivered serial didn't match the config sheet we'd signed. The moral: bring all four documents to the pad, and don't sign anything until three of them match.

In my first year of doing this, we received a crusher that was the right model with the wrong jaw profile. The serial matched, the spec sheet matched, but the physical jaw die was flat-profile when our spec called for corrugated. Nobody caught it for three days of commissioning. Cost us a full teardown and a $4,000 liner swap—and the vendor, reasonably, argued it was within "standard delivery tolerance." Now every contract specifies the jaw profile in writing. Since then, when I compared new deliveries against a control unit side by side, I finally understood why a tiny difference in the spec language changes the whole negotiation.

Step 2: Walk the Wear Components

Jaw plates, cheek plates, and—on cone crushers—the bowl and mantle liner. Look at them with a bright light, not just the afternoon sun. Check for nicks, gouges, and especially for a mismatched gap on either side of the jaw opening.

Here's a fact that surprises people: on a QJ341 jaw crusher, the CSS (closed-side setting—the working gap between the jaw dies) is often set to a "shipping setting" that's wider than what you'd run in production. The dealer usually resets it during commissioning. Confirm that in writing. If the machine arrives with a gap 40 mm off from your spec, it's not broken—it's just set for transport. But record it before anyone touches a bolt. If the factory set it wrong, that's on their dime, not yours.

Step 3: Check the Lube System Dry

Not "run the machine." Check the lube system while the engine is cold, before the oil warms up and hides a problem. Pull a sample from every sight glass on the machine—hydraulic tank and lube tank included. Hold it against a white background. Milky = water ingress. Dark = contaminated. Honey-colored = normal.

I rejected a delivery once because the lube oil looked like chocolate milk. The dealer tried to tell me it was "just a bit of condensation from shipping." I asked for a written statement that the oil was serviceable. They declined to write it. We flushed the system and they paid for it. Ugh—but better that than a seized bearing six weeks in.

Step 4: Exercise the Hydraulics and the Aux Systems Under No-Load

Run every cylinder through full travel. On a jaw crusher, that's jaw adjust and hydraulic release. On a cone, that's CSS adjust and clamping. Watch the gauges, but more importantly—listen for chatter. A clean hydraulic system sounds like a well-tuned diesel. A bad one sounds like gravel in a coffee can.

While you're in that area, do me a favor and check the auxiliary systems too. The operator cab on a modern 800i has an AC compressor and a dust-filtration circuit that costs a surprising amount to fix if it fails on day two. Nobody on the delivery pad cares about cab comfort until the shift ends and the operator is coughing dust. Run the cab AC for ten minutes. Check that the compressor actually cycles. If it doesn't, that's a warranty item—document it before you sign anything.

Step 5: Verify the Control System Against Your Spec

Modern Sandvik 800i series cone crushers use an ASRi or similar automated setting regulation system. You need to confirm that the software version the machine shipped with matches the version your operations team has trained on—or that you have a documented path to update it.

This one bit us in 2022. Same model cone, new control software, operators spent two shifts trying to use the old sequence. Nothing was broken. It was purely a documentation gap. Now we bring our tablet, open the operator's manual in the cab, and run the first-startup sequence from the manual in front of the delivery technician. If they flinch at a step, we note it and pause delivery until we're both confident. Half of what they warned me about during commissioning only made sense after I ignored it once and watched a mislabeled control order cost us a full day of training.

Step 6: Inspect Structure, Not Paint

Look at every weld seam within reach. Look at the structural steel near the crusher housing and near the feed hopper. Fresh paint covers a lot—but you can feel a bird-crack under a weld with your fingertip in about ten seconds.

Shipping damage is the most common reason for a claim. Some is visible, some isn't. A cracked weld at a lifting lug is a claim. A scuffed decal is not. Be specific about what you're logging, and photograph everything against a tape measure so there's no argument about scale later. (Surprise, surprise—nobody ever argues less when the photos are clear.)

Step 7: Run a Clean Cycle With No Feed

Start the machine. Run it for 15–20 minutes with nothing in the chamber. Watch for vibration outside normal range, watch for overheating bearings, and watch for fluid leaks at every joint. This is the step most good inspectors only get to after lunch, which is wrong—do it before lunch, while the delivery crew is still on site and still willing to fix something.

I made this mistake in my first year: I let the machine warm up, said it looked good, and signed off at 4 PM. The delivery crew drove four hours back to their depot. Next morning the lube pump leaked. Three weeks to schedule a return trip. Three weeks of a stalled crusher, and the "free fix" turned into a very expensive scheduling loss. Now I run step 7 in the morning, always.

Step 8: Get Signatures on a Written Punch List, Not a Handshake

Before the delivery crew leaves, you want two things on the truck: a signed acceptance certificate, and a written punch list of every discrepancy—even minor ones. A missing decal. A loose guard bolt. A cab door that doesn't shut flush.

I know it feels petty to write down "cab door seal needs adjustment" when the machine is otherwise pristine. Write it down anyway. That punch list is your only leverage once the truck rolls out. It turns a verbal "we'll get to it" into a paper trail you can escalate. A verbal list becomes a voicemail. A written list becomes a warranty item.

What To Watch for After the Inspection

Three rules of thumb I've picked up, sometimes at cost:

  • Sign nothing under pressure. If the driver or dealer is pushing you to sign mid-inspection, that's a signal, not a reason to rush. Take the extra 20 minutes.
  • Document, don't stew. If you find an issue, log it the same day, in writing. A week-old issue with photos is still useful. A week-old verbal complaint is not.
  • Buy the line items you actually need. A "bucket golf"-style accessory makes a nice photo at the open house. It won't matter when the jaw is down and the plant is idle. Prioritize wear components and lubricants first.

When This Checklist Doesn't Apply

Honest limitation, because that's how I work: this checklist assumes you're receiving a new or recently refurbished machine with dealer support. If you're buying used from a private seller on a gravel lot, you need a different process—used-oil analysis, full wear survey, and an independent third-party inspector, not a dealer walkthrough. And if you're running a small operation with a single machine and no dedicated quality personnel, several of these steps will feel excessive. They aren't wrong; you just shouldn't skip too many at once.

For operations running more than a handful of units, these eight steps have kept us from accepting machines that would've cost us between $5,000 and $40,000 in redo work. And on the occasions when I skipped a step—I've got the receipts to prove it. As of Q1 2024, that's the honest scorecard.